Why ERP Implementations Cost More Than Anyone Budgeted

Why ERP Implementations Cost More Than Anyone Budgeted

It is the assumption behind almost every ERP budget conversation. Whatever number is agreed at the outset, the real one will be higher. It is worth testing that against data, because the picture turns out to be narrower and more specific than the folklore.

Panorama Consulting's 2026 ERP Report surveyed 170 organisations with a median annual revenue of $200.5 million and a median project timeline of nine months.

On budget: 50.6% completed on budget and 19.4% came in below it, so 70% landed at or under the original figure. Of the remainder, 22.9% ran slightly over and 7.1% significantly over.

On schedule: 58.8% finished on time and 18.8% finished early, so 77.6% landed on schedule or better. 18.2% ran slightly late and 4.1% significantly late.

So the premise in the headline holds for roughly three projects in ten. Which makes the more useful question not why ERP costs more, but what distinguishes the minority where it does.

Where overruns actually come from

Respondents whose projects went over could cite more than one cause, and the pattern is consistent.

Among those over budget, the most frequently cited reason was additional technology needing to be purchased to meet project goals, at 54.9%, followed closely by scope expansion at 51.0%. Panorama's own reading is worth quoting: unexpected technology needs are often the result of poor system selection, where organisations discover fatal misfits late in the project and respond with additional technology, scope expansion and custom builds.

Note the timing in that. The money is spent during implementation. The decision that caused it was made during selection.

Among those over schedule, the leading cause was organisational issues at 57.9%, again with scope expansion close behind at 55.3%. The report observes that technical execution often proceeds as planned while approvals, sign-offs and cross-functional alignment trail behind, extending timelines without any increase in scope.

Change management sits underneath this. Only 23.5% of organisations reported an intense focus on it, though a further 64.7% reported a moderate focus and just 11.8% reported very little or none. So it is not being ignored. It is simply rarely treated as a priority, often with the the organisation taking this process on internally, while organisational issues remain the single most cited cause of delay.

Demand for outside help in these areas is climbing. Among organisations that sought third-party guidance, requests for business process management support rose from 40.4% to 50.0% year on year, organisational change management from 38.4% to 46.8%, and post-implementation benefits realisation from 28.3% to 42.1%.

Panorama's conclusion is that with modern cloud and modular ERP, most vendors can meet baseline functional requirements, and that ERP problems most often trace to unclear process ownership, poor user adoption and weak alignment on project goals.

What that means if you are evaluating Business Central

Technical problems do feature, cited by 43.1% of over-budget projects and 50.0% of late ones. But they sit below fit and organisational readiness in both lists, and the great majority of projects land close to plan.

The risks worth planning around are choosing something that does not quite fit and finding out late, and underestimating how much has to change inside the organisation. Both are settled before and around the implementation rather than inside it, and neither is solved by finding a partner with faster developers.

Worth asking yourself before an ERP decision rather than after it: how confident are we that this system genuinely fits, and are we confident in our ability to bring about change internally, focussing on adoption and ownership?

Choosing a partner for the part that carries the risk

If the exposure sits in fit and organisational readiness rather than build speed, that is what a partner is worth judging on. Three questions are more revealing than a day rate:

  • Will they challenge a request and outline whether the system genuinely fits before anyone writes a specification?
  • Will they tell you plainly what is not in the scope they have quoted?
  • Are the people who scoped the work the people who will deliver it?

Ask those of any partner, us included. It is important that the word 'partner' is taken literally in this case, the partners brought in for consideration should be an extension of your team, they should be clear, transparent and protect your interests - sometimes that requires challenge and honesty. 

Scope compression is not automatically a problem, and budgets are finite. A project where the client knowingly takes on its own data cleansing is entirely reasonable. A project where nobody said so until month six is not. The difference is whether the conversation happened. It is about ensuring the partner of choice is one that will have those conversations, when it matters most. 

On the third question our answer is straightforward: delivery is in-house with certified teams rather than subcontracted, so the people who scope your project are the ones who run it. TEKenable has been delivering technology transformation for more than 20 years and holds Business Central Advanced Specialisation from Microsoft, independently verified. We have a diverse and experienced team who are able to safely navigate you to success, whilst also delivering a heartfelt service. 

With the complexity of ERP projects in the modern day, it is to be expected that challenges will arise, the right partner whilst must have demonstratable expertise, should also be judged on the ability to respond and navigate challenges pragmatically, with precision and empathy. 

f you are weighing up Business Central, or reviewing a project already under way, we are happy to talk it through. Call +44 (0) 207 183 8996 or get in touch at tekenable.com/contact-us/.