How to apply non-working hours from a Calendar Template in Dynamics 365 Project Operations & PSA

July 12 2021

Microsoft Dynamics 365 Project Operations and Project Service Automation (PO/PSA) users generally believe that non-working hours cannot be copied from one template resource to another resource when the Calendar template is assigned. They tend to assume that the working shifts and the weekends marked are the only ones that gets copied.

But that is not the case. There is a minor catch in how we do it. This article will help you set up a Calendar template with a resource that contains a template resource that has the non-working hours in the Work hours.

The solution

Perform the following steps to get to results explained above.

Step 1:

Add a non-working hour in the template of the resource by following the screenshots below. We will start by going to Settings and the Calendar Templates screen, which displays the Work template.

Step 2:

Click on the Template Resource and add a non-working hour as shown below in the screenshot.

About Kuldeep Gupta

Kuldeep Gupta is a Microsoft MVP. 

More about Kuldeep Gupta

Comments

hnno1982's picture

I need to Thank you for this great artical


Madelein's picture

How can you make the same day a reccuring non-working day in the template?


Madelein's picture

How do you make one template default? - Or is it standard that all resources is added with work-hours 00-24?